It is a very simple process to edit or make changes to existing templates.
To access the Event Template A list of task definitions that contain the definition of how a new event is to bescheduled in the system. Event templates describe what tasks depend on other tasks,the average duration of each task and the manner in which resources are chosen forassignment to each task in the event. Master from the desktop, select AppWright System Setup and then select Event Template Master. You will then see a list of your templates on the right. By clicking on the name of a template you can select and edit a template.

To view the
tasks for this template click the
button and you will see
a screen similar to the one below.

You can edit just a predecessor of a task by clicking on the link under the Predecessors column. By clicking on Edit next to a particular task you will see the details of that task as shown below.

Event and Task Identification
Sequence
Each step (task) in an event must be given a unique sequence number. This sequence number will be used throughout the definition of event tasks to indicate the relationship(s) between one task and another.
Task Description
Each task must be given a task description to be shown in the WorkList. If this task description is one that can be changed when a job is scheduled then you will want to check the Allow Change? box. At the time of scheduling this task will have a place to enter the new task description.
Task Alias
This is an optional field for entry of a shortened version of the task description which will be used when logging into AppWright with a PDA etc.
Task Status Options
Secure Close?
If this is checked then only worklist administrators will be allowed to close this task or mark it 100% complete. Usually this is checked on a final task of a job to ensure the job is not closed until an administrator has reviewed it first.
Milestone
This box should be checked if this task is to be considered a milestone task. A milestone task will show up in blue bold text so it is easily recognizable from the other tasks in the list. A completed milestone task usually marks when an important goal has been reached in the job.
Resource Any item that can have work assigned to it. Examples: Personnel, equipment, places,work queues Identification/Selection
Source
Each task in an event will eventually be assigned to one resource in the system during the scheduling process. The dropdown selection next to Source is used to define what the “source” of this resource should be (during scheduling).

1 = One specific resource: This option means just what it says; you will name a specific resource on this screen which will always be assigned to this task in this event during the scheduling process.
G = Select from a group of resources: If this option is chosen, you will be asked to identify a named resource group. All members of this group will be presented to you in a list during the scheduling process where you must then select the appropriate resource to assign to the task.
C = Copy a previous resource selected in this event: Choose this option to use the same resource that was assigned to a previous task. You will be asked to identify (by sequence number) the prior task that you wish to copy from. At scheduling time, whatever resource is assigned to the "copy from" task will also be assigned to this task automatically.
R = Use additional resource selection criteria rules: To build complex selection criteria involving and/or relationships between members of resource groups and possible zip code based distance measurements, use this option. You will be given a button to access the selection criteria construction screen and to enter an optional zip code mileage limit, if desired.
P = Prompt for a single resource during scheduling: This option is most commonly used for the customer identification record in an event. During scheduling you can select a single resource from a selection window, though it will generally already be filled in from information in the order screen.
Depending on which option is selected more choices will be given to assign a resource from a group or type. To Allow Change? of these settings at the time of scheduling then just check the appropriate box.
Once you
have completed your settings you will want to select the
button at the bottom left corner. You
will then see a screen similar to the one below.

Predecessor Task
Predecessor
The first thing you will want to select on this screen is the Predecessor, which is the task that should be completed before the start of the current task.
Relationship Task
The Relationship Type should be defined next. There
are several options for the relationship type which will define how the
predecessor task should trigger the current task. In
the illustration “Finish to Start” is selected. This
would mean the finish of the predecessor task will trigger the start of
the current task.
Slack Days
The Slack Days is how many days between the predecessor task and the current task (this is based on the relationship type selection). In the screen above, the “Slack Days” is 1 with a “Finish to Start” relationship type. This will start the current task 1 day after the finish of the predecessor task.
Duration
Calculation
Under the Duration heading you will need to fill in the Calculation
field.
Fixed Duration - will simply let you input the length of time the task should take to be completed.
Variable by Input [Time] - will prompt you for the duration when entering a new job.
Use Input from Previous Task - will display a dropdown field that will let you select a previous task to copy the duration from.
Email Notifications
Task Assignment
Email notification can be used to notify the resource that is assigned this task when the task is assigned. Email can be sent to the primary email address for that resource and/or an alternate address (cell/pager).
Discussions
The options here will allow you to set when posts regarding this task should be sent to the resource assigned.
Updates (Templates, Existing Jobs, Data Screens, Reports)
Finally, there are several options for updating other templates, data collection screens and reports when changes are made to an event task. It is usually recommended, if you are editing tasks, to do these updates. These updates include updating same tasks in other templates, updating current jobs that have the task with the changes and updating all data collection screens and reports that are pulling information from the task being changed.
When all
information is entered, click on the
button at the bottom
left corner of the screen.
By following this process, tasks can be entered one following the other until the template is complete. Tasks can be moved up or down in the template at any time by simply changing the predecessor. The sequence number can be changed as well but this is not necessary. The “Auto Sequence” button on the top of the task list screen will renumber the tasks. The “Check Relations” and “Test Schedule” buttons, also located on the top of the task list, will notify you of any relational problems between the tasks and allow you to run through a test order to view the template.